This quick-start guide briefly covers the installation and operation of the Pantheon HS3 Additive Manufacturing System. More detailed information regarding the topics of this guide can be found in the rest of this user portal.

Note

It is recommended to perform all the installation steps at the machine. Do not perform operations from the web console that result in motion of the printer unless directly present, i.e. sitting in front of it with a computer.

Installation

Note

Status
colourYellow
titleCAUTION
Failure to completely follow the instructions in this section may result in operator injury or damage to the machine. Do not begin the installation procedure unless all preparations for installation are taken or completed. Read the entirety of each instruction before beginning the task. Only perform the tasks in the order they are listed.

...

  • Allow yourself ample space to unbox and install the machine.

  • The machine alone weighs approximately 65 kg (143lbs) and thus requires two people to lift or move.

  • The machine should be operated indoors within the nominal temperature range of 10-35℃.

  • The machine should be placed on a rigid and level surface. You need a sturdy table, a cheap IKEA table will break and drop the printer on the floor!

  • The recommended space requirements for the machine are 100 cm by 70 cm with at least 120 cm height to allow for the enclosure lid to open. If placed on a table or work surface, the surface should be able to support 65 kg. See Table Options for HS3 for an idea of what we recommend.

  • The machine is powered from a standard 120VAC 15A wall outlet.

  • A strong and secured wireless network or ethernet connection is required.

Installation

...

Video

Note

Status
colourYellow
titleCAUTION
Use protective gloves when removing the machine from the shipping box.

...

Installation Steps

  • Using a hammer to bend back the tabs at the edges and bottom of the crate.

    PXL_20230724_023223831.LOCKED.TS.mp4~3.mp4
  • Remove the Lid of the crate first, then the side panels.

  • Remove the tape securing the door and lid of the machine.

  • Remove the protective plastic film from the machine

  • Using a 1/4” socket, or an empty multi-bit screwdriver, remove the brackets securing the machine feet to the crate base (4 pieces in total).

  • Inspect for any damage that may have occurred during shipping.

...

Connecting to your network

...

Wi-Fi

Note

The WiFi Wi-Fi screen currently may take a long time to load. If after 5 minutes no networks appear, reboot the machine and try again. If the problem persists, contact support: support@pantheondesign.ca

...

  • plug your ethernet cable into the ethernet jack on the back of the HS3, its located above the power cord receptacle

  • It may take 1-2 minutes for the ethernet to connect

Connecting to the

...

Web Interface

Please connect to the web interface to validate that the network connection is active

...

Panel
panelIconIdatlassian-warning
panelIcon:warning:
bgColor#FFFAE6

If you’re unable to access the web interface, contact support: support@pantheondesign.ca

The First Print

  • Using the touchscreen on the machine, navigate to the homing page and press home all.

  • Navigate to the move panel on the screen and move the Z axis down by pressing the Z- button. Move the axis to Z=250.

  • Install the smooth or textured bed. Be sure to remove any protective film from the smooth bed. Align with the two pins at the back of the heated plate.

  • See the Load and Unload Filament instructions to install filament.

  • Once filament is loaded, see the Running A Print On The HS3 instructions.

...